Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
25W1156 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /167915 /2023 (ई0 फाईल सं0 56071) दि0 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.26
Resanction Cost :
104.26
Tentative Cost :
104.26
Exp. Upto Last Fy : 83.32
For CFY 2024-2025
Remaining : 20.94
Demand : 20.00
Allotment : 15.00
Exp in CFY : 20.22
Total Up to Date Exp : 103.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
2 months 3 weeks from now
10 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-May-2024
Physical Peramenters