Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.35 | 0.35 | 0.000 | 0.35 | 0.350 | 0.000 |
25W1161 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय जिलाधिकारी ऊधमसिंहनगर का पत्रांक 1558/जि0यो0/अनु0संशोधन/2023-24 दि0 15.12.2023
TS Amount (lakhs) : 24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.00
Resanction Cost :
24.00
Tentative Cost :
24.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 24.00
Demand : 18.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 75 %
Sanction on :
7 months 2 days ago
15 Dec 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 27-Jun-2024
Physical Peramenters