Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.16 | 0.16 | 0.000 | 0.16 | 0.160 | 0.000 |
25W1163 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय जिलाधिकारी ऊधमसिंहनगर का पत्रांक 1550/जि0यो0-35/वि0प्रशा0स्वी0/लो0नि0वि0/2023-24 दि0 15.12.2023
TS Amount (lakhs) : 16 Lacs
Financial Detail
Sanction Cost : 16.00 Lacs
Resanction Cost : 16.00 Lacs
Exp. Upto Last Fy : 2.82 Lacs
For CFY 2024-2025
Remaining : 13.18 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.82 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 months 4 days ago
15 Dec 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण शेष कार्य प्रगति में -- as on 11-Apr-2024