Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.350 | 0.000 |
25W1170 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /181012 /2024 (ई0 फाईल सं0 56071) दि0 10.01.2024
TS Amount (lakhs) : 48.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.49
Resanction Cost :
48.49
Tentative Cost :
48.49
Exp. Upto Last Fy : 35.94
For CFY 2024-2025
Remaining : 12.55
Demand : 10.00
Allotment : 2.00
Exp in CFY : 0.67
Total Up to Date Exp : 36.61
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 100 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
3 weeks 3 days from now
11 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 27-Jun-2024
Physical Peramenters