Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.765 | 0.765 | 0.000 | 0.765 | 0.000 | 0.000 |
25W1171 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /181012 /2024 (ई0 फाईल सं0 56071) दि0 10.01.2024
TS Amount (lakhs) : 71.5 Lacs
Financial Detail
Sanction Cost : 71.50 Lacs
Resanction Cost : 71.50 Lacs
Exp. Upto Last Fy : 0.07 Lacs
For CFY 2024-2025
Remaining : 71.43 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.07 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
4 months 1 week ago
10 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग के दोनों ओर साईड वाल का कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters