Work Profile Report [25W1172]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /181012 /2024 (ई0 फाईल सं0 56071) दि0 10.01.2024
TS Amount (lakhs) : 66.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.90
Resanction Cost :
66.90
Tentative Cost :
46.25
Saving
20.65
Exp. Upto Last Fy :
10.46
For CFY 2024-2025
Remaining :
56.44
Demand :
40.00
Allotment :
10.00
Exp in CFY :
5.12
Total Up to Date Exp :
15.57
Construction Started
Sanction on : 10 months 1 week ago
10 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
65 %
Tentative Completion date on : 3 months 1 week from now
03 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 28-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: