Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.000 | 0.7 | 0.700 | 0.000 |
25W1172 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /181012 /2024 (ई0 फाईल सं0 56071) दि0 10.01.2024
TS Amount (lakhs) : 66.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.90
Resanction Cost :
66.90
Tentative Cost :
66.90
Exp. Upto Last Fy : 10.46
For CFY 2024-2025
Remaining : 56.44
Demand : 40.00
Allotment : 5.00
Exp in CFY : 0.78
Total Up to Date Exp : 11.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 50 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
1 month 3 weeks from now
12 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टर कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 27-Jun-2024
Physical Peramenters