Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
25W1173 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /184680 /2024 (ई0 फाईल सं0 54118) दि0 24.01.2024
TS Amount (lakhs) : 94.46 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.46
Resanction Cost :
94.46
Tentative Cost :
94.46
Exp. Upto Last Fy : 13.00
For CFY 2024-2025
Remaining : 81.46
Demand : 50.00
Allotment : 50.00
Exp in CFY : 23.51
Total Up to Date Exp : 36.51
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
5 months 3 weeks ago
24 Jan 2024
Tentative Completion date:
4 months 5 days from now
23 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टर कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 27-Jun-2024
Physical Peramenters