Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
25W1182 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /196330 /2024 (ई0 फाईल सं0 68062) दि0 06.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 36.30 Lacs
Resanction Cost : 36.30 Lacs
Exp. Upto Last Fy : 0.08 Lacs
For CFY 2024-2025
Remaining : 36.22 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.08 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 1 week ago
06 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा आमंत्रित -- as on 11-Apr-2024
Physical Peramenters