Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.52 | 3.52 | 0.000 | 3.52 | 0.000 | 0.000 |
25W1183 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 ।/198898/2024 (ई0 फाईल सं0- 68208) दि0 14.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
189.70
Resanction Cost :
189.70
Tentative Cost :
189.70
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 189.60
Demand : 140.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 3 days ago
14 Mar 2024
Tentative Completion date:
11 months 1 week from now
30 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा निस्तारण की कार्यवाही दि0 20.07.24 तक पूर्ण कर ली जायेगी। -- as on 01-Jul-2024