Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.26 | 2.26 | 0.000 | 2.26 | 0.000 | 0.000 |
25W1185 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 ।/197218/2024 (ई0 फाईल सं0- 65779) दि0 11.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
351.63
Resanction Cost :
351.63
Tentative Cost :
351.63
Exp. Upto Last Fy : 0.08
For CFY 2024-2025
Remaining : 351.55
Demand : 249.50
Allotment : 175.00
Exp in CFY : 89.65
Total Up to Date Exp : 89.73
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 50 %
Sanction on :
4 months 6 days ago
11 Mar 2024
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0एम0एम0 प्रथम लेयर का कार्य पूर्ण शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters