Work Profile Report [25W1186]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/198802/2024 (ई0 फाईल सं0- 68041) दि0 14.03.2024
TS Amount (lakhs) : 77.03 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.03
Resanction Cost :
77.03
Tentative Cost :
52.00
Saving
25.03
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
76.93
Demand :
40.00
Allotment :
13.00
Exp in CFY :
9.84
Total Up to Date Exp :
9.94
Construction Started
Sanction on : 8 months 1 week ago
14 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 4 months 1 week from now
03 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डब्लू0एम0एम0 का कार्य पूर्ण, नाला निर्माण कार्य प्रगति में। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: