Work Profile Report [25W1213]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/283314/2025 (ई0 फाईल सं0 47605) दि0 18.03.2025
TS Amount (lakhs) : 71.87 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
71.87
Resanction Cost :
71.87
Tentative Cost :
71.87
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
71.77
Demand :
64.00
Allotment :
24.25
Exp in CFY :
24.25
Total Up to Date Exp :
24.34
Construction Started
Sanction on : 4 months 9 hours ago
18 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
45 %
Tentative Completion date on : 3 months 2 weeks from now
07 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 01-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: