Work Profile Report [25W1223]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/285828/2025 (ई0 फाईल सं0 68062) दि0 25.03.2025
TS Amount (lakhs) : 38.3 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
38.30
Resanction Cost :
38.30
Tentative Cost :
38.30
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
38.20
Demand :
35.00
Allotment :
13.19
Exp in CFY :
13.19
Total Up to Date Exp :
13.29
Construction Started
Sanction on : 4 months 2 weeks ago
25 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 6 months 1 week from now
18 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इण्टर कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 01-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: