Work Profile Report [2W163]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 549/111(2)/ 14 -49 (प्रा0आ0)/13 दिनाॅक 29/1/2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.32
Resanction Cost :
15.32
Tentative Cost :
0.09
Saving
15.23
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
15.23
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.09
Work completed
Sanction on : 11 years 6 months ago
29 Jan 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 4 months ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
900मी0 में द्वितीय चरण की स्वीकृति प्राप्त। कार्य प्रगति पर है। -- as on 16-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: