Work Profile Report [2W186]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं.6581/।।।(2)/10-49(एम.एल.ए.)/10 दि0 4.3.11
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.90
Resanction Cost :
39.90
Tentative Cost :
0.24
Saving
39.66
Exp. Upto Last Fy :
0.24
For CFY 2025-2026
Remaining :
39.66
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.24
Alignment Approved
Sanction on : 14 years 5 months ago
04 Mar 2011
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 9 months 4 days ago
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में वनभूमि हस्तान्तरण प्रस्ताव ऑनलाइन प्रभागीय वनाधिकारी स्तर पर प्रदर्शित हो रहा है। -- as on 13-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand