Work Profile Report [2W25]

मकड़ाऊ-दशौला मोटर मार्ग (किमी. 1-5)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2120/।।।(2)/16-08(प्रा.आ.)/2004टी.सी. दि0 11-07-2016

TS Amount (lakhs) : 155.98 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

155.98

Resanction Cost :

155.98

Tentative Cost :

155.98

Exp. Upto Last Fy :

85.80

For CFY 2025-2026

Remaining :

70.18

Demand :

4.00

Allotment :

7.15

Exp in CFY :

7.15

Total Up to Date Exp :

92.95

Construction Started

Sanction on : 9 years 6 months ago

11 Jul 2016

Physical Progress:

At start of FY 2025-2026 :

78 %

Up to Date :

80 %

Tentative Completion date on : 1 year 7 months from now

31 Aug 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
3.500
1.5
0.000
0.000

Remark

view all

मार्ग के अंतिम 100 मीटर में नाप भूमि में विवाद होने के कारण कार्य का अनीतिमीकरण किया जा रहा है। विधिवत स्वीकृति अपेक्षित। -- as on 02-Jan-2026

Rating : 78

Forest Case Pending At : 12: AIP DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand