Work Profile Report [2W253]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 148/।।।(2)/16-59(प्रा.आ.)/2015 दि0 13.01.2016
TS Amount (lakhs) : 452.07 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
452.07
Resanction Cost :
452.07
Tentative Cost :
347.97
Saving
104.10
Exp. Upto Last Fy :
332.36
For CFY 2025-2026
Remaining :
119.71
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
332.36
In Maintenance After Completion
Sanction on : 9 years 6 months ago
13 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 4 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य 3 /2022 में पूर्ण । कार्य की पीे0सी0सी0 प्रेषित। -- as on 16-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: