Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
2W253 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 148/।।।(2)/16-59(प्रा.आ.)/2015 दि0 13.01.2016
TS Amount (lakhs) : 452.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
452.07
Resanction Cost :
452.07
Tentative Cost :
452.07
Exp. Upto Last Fy : 329.25
For CFY 2024-2025
Remaining : 122.82
Demand : 3.12
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 329.25
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 6 months ago
13 Jan 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य 3 /2022 में पूर्ण p c c प्रेषित। -- as on 04-Jul-2024
Physical Peramenters