Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.5 | 7.5 | 3.000 | 4.5 | 4.500 | 3.000 |
No of Bridges | 3 | 3 | 0 | 3 | 1 | 1 |
2W275 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 665/।।।(2)/16-48(एम.एल.ए.)/2015 दि0 29.02.2016
TS Amount (lakhs) : 455.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
455.89
Resanction Cost :
455.89
Tentative Cost :
455.89
Exp. Upto Last Fy : 230.97
For CFY 2024-2025
Remaining : 224.92
Demand : 150.00
Allotment : 50.00
Exp in CFY : 69.01
Total Up to Date Exp : 299.97
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
8 years 4 months ago
29 Feb 2016
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान कार्य पूर्ण। पार्ट 2 व सेतु का कार्य प्रगति पर। -- as on 17-Apr-2024
Physical Peramenters