Work Profile Report [2W334]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2485/।।।(2)/16-53(एम.एल.ए.)/2015 दि0 21.09.2016
TS Amount (lakhs) : 230.97 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
230.97
Resanction Cost :
230.97
Tentative Cost :
230.97
Exp. Upto Last Fy :
210.97
For CFY 2025-2026
Remaining :
20.00
Demand :
10.00
Allotment :
0.25
Exp in CFY :
0.25
Total Up to Date Exp :
211.22
Work completed
Sanction on : 8 years 10 months ago
21 Sep 2016
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 4 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान। -- as on 17-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: