Work Profile Report [2W404]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1306/।।।(2)/19-52(एम0एल0ए0)/2017 दि0 07.03.2019
TS Amount (lakhs) : 37.52 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.52
Resanction Cost :
37.52
Tentative Cost :
37.52
Exp. Upto Last Fy :
4.04
For CFY 2025-2026
Remaining :
33.48
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.04
Alignment Approved
Sanction on : 6 years 4 months ago
07 Mar 2019
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 7 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण स्वीकृत। वन विभाग के साथ संयुक्त निरीक्षण हेतु पत्र प्रेषित। -- as on 23-Sep-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand