Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
2W463 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1394(।)/।।।(2)/21-52(एम0एल0ए0) /2017 दि0 25.05.2021
TS Amount (lakhs) : 136 Lacs
Financial Detail
Sanction Cost : 136.00 Lacs
Resanction Cost : 136.00 Lacs
Exp. Upto Last Fy : 50.16 Lacs
For CFY 2024-2025
Remaining : 85.84 Lacs
Demand : 15.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 50.16 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
2 years 11 months ago
25 May 2021
Tentative Completion date:
1 year 7 months ago
30 Sep 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य 3 / 2023 में पूर्ण -- as on 17-Apr-2023