Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
2W466 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1471/।।।(2)/21-21(प्रा0आ0)/ 2017 दि0 04.06.2021
TS Amount (lakhs) : 81.68 Lacs
Financial Detail
Sanction Cost : 81.68 Lacs
Resanction Cost : 81.68 Lacs
Exp. Upto Last Fy : 26.04 Lacs
For CFY 2024-2025
Remaining : 55.64 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 26.04 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
2 years 11 months ago
04 Jun 2021
Tentative Completion date:
2 years 2 months ago
02 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.00 किमी0 पहाड़ कटान का कार्य पूर्ण। शेष 0.50 किमी0 में ग्रावासियों द्वारा विवाद। -- as on 06-Nov-2023