Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 39 | 39 | 0.000 | 39 | 0.000 | 0.000 |
2W497 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: सकार झुलापुल
Administrative Approval Detail : G.O. No. 1098/III(3)/2021-34 (C.R.I.F.}/2021 Dt. 04-10-2021
TS Amount (lakhs) : 591.42 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
591.42
Resanction Cost :
591.42
Tentative Cost :
591.42
Exp. Upto Last Fy : 514.00
For CFY 2024-2025
Remaining : 77.42
Demand : 52.00
Allotment : 52.00
Exp in CFY : 38.02
Total Up to Date Exp : 552.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 92 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
04 Oct 2021
Tentative Completion date:
3 months 2 days ago
15 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Jul-2024
Physical Peramenters