Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 39 | 39 | 0.000 | 39 | 0.000 | 0.000 |
2W497 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: सकार झुलापुल
Administrative Approval Detail : G.O. No. 1098/III(3)/2021-34 (C.R.I.F.}/2021 Dt. 04-10-2021
TS Amount (lakhs) : 591.42 Lacs
Financial Detail
Sanction Cost : 591.42 Lacs
Resanction Cost : 591.42 Lacs
Exp. Upto Last Fy : 514.00 Lacs
For CFY 2024-2025
Remaining : 77.42 Lacs
Demand : 52.00 Lacs
Allotment : 52.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 514.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 92 %
Up to Date : 92 %
Sanction on :
2 years 7 months ago
04 Oct 2021
Tentative Completion date:
3 months 3 weeks ago
26 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1- पैरापिट निर्माण एवं क्रैष बैरियर का कार्य पूर्ण।
2- रोड सेफ्टी के अन्य कार्य प्रगति पर ।
-- as on 15-Mar-2024
Physical Peramenters