Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 36 | 36 | 0.000 | 36 | 36.000 | 0.000 |
2W503 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5441/।।।(2)/21-51(एम0एल0ए0)/ 2017 दि0 12.11.2021
TS Amount (lakhs) : 239.28 Lacs
Financial Detail
Sanction Cost : 239.28 Lacs
Resanction Cost : 239.28 Lacs
Exp. Upto Last Fy : 219.19 Lacs
For CFY 2024-2025
Remaining : 20.09 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 219.19 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 78 %
Up to Date : 78 %
Sanction on :
2 years 6 months ago
12 Nov 2021
Tentative Completion date:
3 weeks 5 days from now
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इरेक्शन का कार्य पूर्ण । पहुॅच मार्ग का कार्य प्रगति पर है। -- as on 31-Jan-2024
Physical Peramenters