Work Profile Report [2W504]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5441/।।।(2)/21-51(एम0एल0ए0)/ 2017 दि0 12.11.2021
TS Amount (lakhs) : 163.69 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
163.69
Resanction Cost :
163.69
Tentative Cost :
163.69
Exp. Upto Last Fy :
159.25
For CFY 2024-2025
Remaining :
4.44
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
159.25
Work completed
Sanction on : 3 years 1 month ago
12 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 01-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: Naikane