Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 24 | 24 | 0.000 | 24 | 24.000 | 0.000 |
2W509 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6582/।।।(2)/21-51(एम.एल.ए.)/2017 दि0 31.12.2021
TS Amount (lakhs) : 159.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
159.31
Resanction Cost :
159.31
Tentative Cost :
159.31
Exp. Upto Last Fy : 16.83
For CFY 2024-2025
Remaining : 142.48
Demand : 130.00
Allotment : 15.00
Exp in CFY : 15.00
Total Up to Date Exp : 31.83
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
2 years 6 months ago
31 Dec 2021
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। कार्य को शीघ्र पूर्ण करने हेतु ठेकेदार को कई बार नोटिस जारी किये गये हैं। -- as on 13-Jul-2024
Physical Peramenters