Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 30.000 | 0.000 |
2W510 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6582/।।।(2)/21-51(एम.एल.ए.)/2017 दि0 31.12.2021
TS Amount (lakhs) : 262.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
262.78
Resanction Cost :
262.78
Tentative Cost :
262.78
Exp. Upto Last Fy : 169.59
For CFY 2024-2025
Remaining : 93.19
Demand : 90.00
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 169.59
Construction Started
Physical Progress:
At start of FY 2024-2025 : 62 %
Up to Date : 81 %
Sanction on :
2 years 6 months ago
31 Dec 2021
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दिनांक 30.09.2024 तक कार्य पूर्ण कर लिया जायेगा। कार्यस्थल पर पहुंच मार्ग एवम रिटर्न वाल का कार्य प्रगति पर है । कार्य को शीघ्र पूर्ण करने हेतु ठेकेदार को नोटिस जारी किये गये हैं। -- as on 13-Jul-2024