Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
2W513 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 447/III(2)/21-51(MLA)/2017
TS Amount (lakhs) : 129.74 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
129.74
Resanction Cost :
129.74
Tentative Cost :
129.74
Exp. Upto Last Fy : 123.18
For CFY 2024-2025
Remaining : 6.56
Demand : 0.57
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 123.18
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य 6 /2023 में पूर्ण। -- as on 04-Jul-2024
Physical Peramenters