Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.2 | 3.2 | 2.000 | 1.2 | 1.200 | 1.000 |
2W578 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file no. 38879 dated 15/03/2023
TS Amount (lakhs) : 179.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
179.78
Resanction Cost :
179.78
Tentative Cost :
179.78
Exp. Upto Last Fy : 111.06
For CFY 2024-2025
Remaining : 68.72
Demand : 64.00
Allotment : 20.93
Exp in CFY : 27.76
Total Up to Date Exp : 138.81
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 86 %
Sanction on :
1 year 4 months ago
15 Mar 2023
Tentative Completion date:
2 months 3 days from now
21 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 की. मी. मार्ग यातायात योग्य शेष में कार्य प्रगति पर -- as on 03-Jul-2024
Physical Peramenters