Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.13 | 6.13 | 3.000 | 3.13 | 3.130 | 3.130 |
2W590 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता के पत्रांक 895 / 07 याता - पी.एम.ज़ी.एस.वाई.-नि iii दिनाँक 16. 05 .20 23
TS Amount (lakhs) : 147.42 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
147.42
Resanction Cost :
147.42
Tentative Cost :
147.42
Exp. Upto Last Fy : 65.54
For CFY 2024-2025
Remaining : 81.88
Demand : 59.00
Allotment : 50.00
Exp in CFY : 51.29
Total Up to Date Exp : 116.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
27 May 2024
Actual Completion Date:
1 month 2 weeks ago
27 May 2024
Remark
Bottelneck: no issue
कार्य भौतिक रूप से पूर्ण। कार्य का अंतिम विचलन एवं समयवृद्धि प्रकरण स्वीकृति हेतु प्रेषित किया जा रहा है। -- as on 01-Jul-2024
Physical Peramenters