Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.13 | 6.13 | 3.000 | 3.13 | 3.130 | 1.000 |
2W590 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता के पत्रांक 895 / 07 याता - पी.एम.ज़ी.एस.वाई.-नि iii दिनाँक 16. 05 .20 23
TS Amount (lakhs) : 147.42 Lacs
Financial Detail
Sanction Cost : 147.42 Lacs
Resanction Cost : 147.42 Lacs
Exp. Upto Last Fy : 65.54 Lacs
For CFY 2024-2025
Remaining : 81.88 Lacs
Demand : 59.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 6.20 Lacs
Total Up to Date Exp : 71.74 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 65 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 3 weeks ago
28 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार,कल्वर्ट, नाली,पैरापिट निर्माण कार्य पूर्ण।पी सी का कार्य प्रगति पर। -- as on 15-Mar-2024
Physical Peramenters