Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.65 | 7.65 | 4.000 | 3.65 | 3.650 | 3.650 |
2W591 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता के पत्रांक 895 / 07 याता - पी.एम.ज़ी.एस.वाई.-नि iii दिनाँक 16. 05 .2023
TS Amount (lakhs) : 108.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
108.47
Resanction Cost :
108.47
Tentative Cost :
108.47
Exp. Upto Last Fy : 50.17
For CFY 2024-2025
Remaining : 58.30
Demand : 51.00
Allotment : 50.00
Exp in CFY : 39.37
Total Up to Date Exp : 89.54
Construction Started
Physical Progress:
At start of FY 2024-2025 : 52 %
Up to Date : 95 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 1 week from now
27 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार,कल्वर्ट, नाली,पैरापिट निर्माण,पी सी का कार्य पूर्ण। पटरी भरान का कार्य प्रगति पर। -- as on 06-Jun-2024
Physical Peramenters