Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14 | 14 | 2.000 | 12 | 12.000 | 10.000 |
2W593 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता के पत्रांक 895 / 07 याता - पी.एम.ज़ी.एस.वाई.-नि iii दिनाँक 16. 05 .2023
TS Amount (lakhs) : 355.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
355.02
Resanction Cost :
355.02
Tentative Cost :
355.02
Exp. Upto Last Fy : 62.77
For CFY 2024-2025
Remaining : 292.25
Demand : 260.00
Allotment : 107.00
Exp in CFY : 104.25
Total Up to Date Exp : 167.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 48 %
Up to Date : 80 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
5 months 4 weeks from now
15 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार,कल्वर्ट, नाली,पैरापिट निर्माण व 12.00 की.मी. में पी सी का कार्य पूर्ण। 2.00 Km.पी सी व पटरी भरान का कार्य प्रगति पर। -- as on 06-Jun-2024
Physical Peramenters