Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14 | 14 | 2.000 | 12 | 12.000 | 5.000 |
2W593 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता के पत्रांक 895 / 07 याता - पी.एम.ज़ी.एस.वाई.-नि iii दिनाँक 16. 05 .2023
TS Amount (lakhs) : 355.02 Lacs
Financial Detail
Sanction Cost : 355.02 Lacs
Resanction Cost : 355.02 Lacs
Exp. Upto Last Fy : 62.77 Lacs
For CFY 2024-2025
Remaining : 292.25 Lacs
Demand : 260.00 Lacs
Allotment : 107.00 Lacs
Exp in CFY : 13.51 Lacs
Total Up to Date Exp : 76.27 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 48 %
Up to Date : 48 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
7 months 3 weeks from now
15 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार,कल्वर्ट, नाली,पैरापिट निर्माण कार्य पूर्ण। पी सी का कार्य प्रगति पर। -- as on 17-Apr-2024
Physical Peramenters