Work Profile Report [2W61]

सेरासबसील गांव के मध्य कुटौलीगैर में 60मी0 स्पान झूला पुल का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2394/।।।(2)/16-09(प्रा.आ.)/2004 दि0 01.09.2016

TS Amount (lakhs) : 100 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

100.00

Resanction Cost :

100.00

Tentative Cost :

100.00

Exp. Upto Last Fy :

79.45

For CFY 2025-2026

Remaining :

20.55

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

79.45

Construction Started

Sanction on : 8 years 11 months ago

01 Sep 2016

Physical Progress:

At start of FY 2025-2026 :

45 %

Up to Date :

45 %

Tentative Completion date on : 1 year 11 months ago

31 Aug 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (60m)
1 (60m)
1 (60m)
-

Remark

view all

बंायी ओर के एबटमेन्ट की चिनाई 7मी0 पूर्ण। दांये एबटमेन्ट के फाउन्डेशन की राफ्ट का कार्य पूर्ण चिनाई का कार्य प्रगति में है। -- as on 23-Jul-2021

Rating : 79

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: