Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 108.89 | 108.89 | 0.000 | 108.89 | 0.000 | 0.000 |
2W645 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No 1848/III (2) / 23-01 ( Pra. Aa.) /2009 Dt. 16.06.2023
TS Amount (lakhs) : 1096.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1096.85
Resanction Cost :
1096.85
Tentative Cost :
1096.85
Exp. Upto Last Fy : 685.96
For CFY 2024-2025
Remaining : 410.89
Demand : 410.00
Allotment : 209.62
Exp in CFY : 2.49
Total Up to Date Exp : 688.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 1 month ago
16 Jun 2023
Tentative Completion date:
2 months 1 week ago
05 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
17597 मी0 के सापेक्ष 13750 मी0 में कै्रश बैरियर का कार्य पूर्ण। शेष लम्बाई में कै्रश बैरियर एवं 454 नं0 काॅश्नरी व 1760नं0 डेलीनेटर व 2820 नं0 कैटआईज लगाये जाने की कार्यवाही की जा रही है। कार्य प्रगति पर है। -- as on 29-Apr-2024
Physical Peramenters