Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 54.23 | 54.23 | 0.000 | 54.23 | 0.000 | 0.000 |
2W646 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No 1848/III (2) / 23-01 ( Pra. Aa.) /2009 Dt. 16.06.2023
TS Amount (lakhs) : 291.54 Lacs
Financial Detail
Sanction Cost : 291.54 Lacs
Resanction Cost : 291.54 Lacs
Exp. Upto Last Fy : 33.45 Lacs
For CFY 2024-2025
Remaining : 258.09 Lacs
Demand : 258.00 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 33.45 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
11 months 3 days ago
16 Jun 2023
Tentative Completion date:
2 weeks 2 hours ago
05 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पनुवानौला वृद्ध जागेश्वर मोटर मार्ग में 1000मी0 क्रैश बैरियर का कार्य पूर्ण। शेष लम्बाई में कार्य प्रगति पर। -- as on 29-Apr-2024
Physical Peramenters