Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.64 | 5.64 | 3.000 | 2.64 | 2.640 | 2.640 |
2W648 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No 48456
TS Amount (lakhs) : 107.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.91
Resanction Cost :
107.91
Tentative Cost :
107.91
Exp. Upto Last Fy : 29.25
For CFY 2024-2025
Remaining : 78.66
Demand : 78.00
Allotment : 70.00
Exp in CFY : 61.07
Total Up to Date Exp : 90.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
10 months 3 weeks ago
21 Aug 2023
Tentative Completion date:
2 weeks 5 days ago
28 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार , पैरापिट निर्माण पी सी का कार्य पूर्ण । -- as on 06-Jun-2024
Physical Peramenters