Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.64 | 5.64 | 3.000 | 2.64 | 2.640 | 2.640 |
2W648 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No 48456
TS Amount (lakhs) : 107.91 Lacs
Financial Detail
Sanction Cost : 107.91 Lacs
Resanction Cost : 107.91 Lacs
Exp. Upto Last Fy : 29.25 Lacs
For CFY 2024-2025
Remaining : 78.66 Lacs
Demand : 78.00 Lacs
Allotment : 70.00 Lacs
Exp in CFY : 7.01 Lacs
Total Up to Date Exp : 36.26 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
1 month 3 weeks ago
28 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार , पैरापिट निर्माण पी सी का कार्य पूर्ण व पटरी भरान आदि का कार्य प्रगति पर। -- as on 29-Apr-2024
Physical Peramenters