Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.41 | 20.41 | 20.41 | 0 |
2W665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5135(A)/III(2)/2023-01/2023 date 14.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
158.89
Resanction Cost :
158.89
Tentative Cost :
158.89
Exp. Upto Last Fy : 130.59
For CFY 2024-2025
Remaining : 28.30
Demand : 28.00
Allotment : 28.00
Exp in CFY : 0.00
Total Up to Date Exp : 130.59
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
8 months 3 days ago
14 Nov 2023
Tentative Completion date:
1 month 3 weeks from now
12 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रैश बैरियर व डैलिनेटर लगाने का कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 21-Jun-2024