Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.41 | 20.41 | 20.41 | 0 |
2W665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5135(A)/III(2)/2023-01/2023 date 14.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 158.89 Lacs
Resanction Cost : 158.89 Lacs
Exp. Upto Last Fy : 130.59 Lacs
For CFY 2024-2025
Remaining : 28.30 Lacs
Demand : 28.00 Lacs
Allotment : 28.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 130.59 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
6 months 5 days ago
14 Nov 2023
Tentative Completion date:
3 months 3 weeks from now
12 Sep 2024
Actual Completion Date:
2 months 6 days ago
13 Mar 2024
Remark
Bottelneck: no issue
क्रैश बैरियर व डैलिनेटर लगाने का कार्य पूर्ण। -- as on 13-May-2024
Physical Peramenters