Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 85.23 | 85.23 | 85.23 | 0 |
2W666 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5135(A)/III(2)/2023-01/2023 date 14.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
470.57
Resanction Cost :
470.57
Tentative Cost :
470.57
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 470.57
Demand : 470.00
Allotment : 300.00
Exp in CFY : 152.38
Total Up to Date Exp : 152.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 40 %
Sanction on :
8 months 3 days ago
14 Nov 2023
Tentative Completion date:
1 month 3 weeks from now
11 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1500मी0 में क्रैश बैरियर लगाने का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 21-Jun-2024
Physical Peramenters