Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.3 | 18.3 | 0.000 | 18.3 | 0.000 | 0.000 |
2W667 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5347/III(2)/2023-01/2023 date 05.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
255.59
Resanction Cost :
255.59
Tentative Cost :
255.59
Exp. Upto Last Fy : 19.28
For CFY 2024-2025
Remaining : 236.31
Demand : 236.00
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 13 %
Up to Date : 13 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
1 month 3 weeks from now
12 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10नं0 पैरापिट निर्माण पूर्ण। शेष पैरापिट निर्माण व दीवारों का निर्माण कार्य प्रगति पर। -- as on 21-Jun-2024
Physical Peramenters