Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.3 | 18.3 | 18.3 | 0 |
2W667 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5347/III(2)/2023-01/2023 date 05.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 255.59 Lacs
Resanction Cost : 255.59 Lacs
Exp. Upto Last Fy : 19.28 Lacs
For CFY 2024-2025
Remaining : 236.31 Lacs
Demand : 236.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.28 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 13 %
Up to Date : 13 %
Sanction on :
5 months 2 weeks ago
05 Dec 2023
Tentative Completion date:
3 months 3 weeks from now
12 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैरापिट निर्माण का कार्य प्रगति पर। -- as on 15-Mar-2024
Physical Peramenters