Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.2 | 8.2 | 8.200 | 0 | 0.000 | 0.000 |
2W668 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No. 63023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
271.38
Resanction Cost :
271.38
Tentative Cost :
271.38
Exp. Upto Last Fy : 254.08
For CFY 2024-2025
Remaining : 17.30
Demand : 17.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 254.08
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 months 1 week ago
06 Dec 2023
Tentative Completion date:
9 months 2 days ago
15 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 13-Jul-2024
Physical Peramenters