Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.225 | 2.225 | 0.000 | 2.225 | 2.225 | 0.000 |
2W671 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No. 48456 date 30.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.33
Resanction Cost :
67.33
Tentative Cost :
67.33
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 67.33
Demand : 50.00
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 12 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
4 months 3 weeks from now
13 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार व काजवे का कार्य प्रगति पर। -- as on 06-Jun-2024