Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.3 | 14.3 | 0.000 | 14.3 | 14.300 | 0.000 |
2W675 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Efile No. 48456 Dt. 23/02/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
269.55
Resanction Cost :
269.55
Tentative Cost :
269.55
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 269.55
Demand : 266.00
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 8 %
Sanction on :
4 months 3 weeks ago
23 Feb 2024
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार व स्कपर का कार्य प्रगति पर। -- as on 06-Jun-2024
Physical Peramenters