Work Profile Report [2W675]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Efile No. 48456 Dt. 23/02/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
269.55
Resanction Cost :
269.55
Tentative Cost :
269.55
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
269.55
Demand :
266.00
Allotment :
65.60
Exp in CFY :
65.60
Total Up to Date Exp :
65.60
Construction Started
Sanction on : 10 months 1 day ago
23 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
40 %
Tentative Completion date on : 2 months 2 weeks from now
14 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार व स्कपर का कार्य प्रगति पर -- as on 04-Dec-2024
Assets :
© PWD Uttarakhand