Work Profile Report [2W708]

द्यूनाथल बुधाड़ मिरौली मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष कार्यालय का पत्रांक 388/14याता0 (क)-उ0 /2023 दि0 15.03.2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

53.64

Resanction Cost :

53.64

Tentative Cost :

53.64

Exp. Upto Last Fy :

46.57

For CFY 2025-2026

Remaining :

7.07

Demand :

0.00

Allotment :

72.76

Exp in CFY :

72.76

Total Up to Date Exp :

119.32

Work completed

Sanction on : 1 year 4 months ago

15 Mar 2024

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3.21
3.21
3.210
0
0.000
0.000

Remark

view all

3.210 किमी मे पीसी का कार्य पूर्ण। -- as on 25-Oct-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand