Work Profile Report [2W764]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 315 /14 याता0 (क)-उ 0 /2024 -25 दिनांक 03-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
357.07
Resanction Cost :
357.07
Tentative Cost :
357.07
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
357.07
Demand :
0.00
Allotment :
313.69
Exp in CFY :
313.69
Total Up to Date Exp :
313.69
Work completed
Sanction on : 5 months 1 day ago
03 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 12-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand