Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 4.9 | 4.9 | 0 |
2W99 :
Administrative Approval Detail : शा0सं0 3704/।।।(2)/08-49(एम0एल0ए0)/08 दिनंाक 19.11.08 पुनरीक्षित 4494/।।।(2)/19-51(एम0एल0ए0)/17 टी0सी0 दि0 11.12.2019
TS Amount (lakhs) : 272.78 Lacs
Financial Detail
Sanction Cost : 175.00 Lacs
Resanction Cost : 272.78 Lacs
Exp. Upto Last Fy : 175.91 Lacs
For CFY 2024-2025
Remaining : 96.87 Lacs
Demand : 2.73 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 175.91 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 6 months ago
19 Nov 2008
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
कार्य माह 07/2022 में पूर्ण। मांग द्युतीय वर्ष के अनुरक्षण हेतु की गयी है। -- as on 18-Apr-2024
Physical Peramenters