Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.71 | 3.71 | 2.000 | 1.71 | 1.710 | 0.000 |
30W1213 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2188/।।।(2)/19-22(मु0म0घो0)/09 दि0 13-06-19
TS Amount (lakhs) : 360.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
360.41
Resanction Cost :
360.41
Tentative Cost :
360.41
Exp. Upto Last Fy : 212.70
For CFY 2024-2025
Remaining : 147.71
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 212.70
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
5 years 1 month ago
13 Jun 2019
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
मार्ग निर्माण का कार्य 2.00 किमी0 मे पूर्ण। इसके आगे विवाद के कारण कार्य बाधित, जिस पर जिलाधिकारी महोदय के पत्रांक- 209/सी0पी0ओ0 दिनांक 27-05-21 से तहसीलदार डुण्डा द्वारा स्थलीय निरीक्षण किया गया जिस पर आख्या/निर्णय अपेक्षित है। वर्तमान मे चालू अनुबन्ध का विवाद के चलते अन्तिमीकरण किया जा चुका है। शेष 1.71 किमी0 हेतु प्रकरण मा0 उच्च न्यायालय मे विचाराधीन है, जिस कारण कार्य स्थगित है। -- as on 03-May-2024
Physical Peramenters