Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.9 | 0.9 | 0.000 | 0.9 | 0.200 | 0.000 |
30W1242 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 104/रा0यो0आ0/जि0यो0/2020-21 दि0 05-11-20
TS Amount (lakhs) : 30 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.44
Resanction Cost :
89.44
Tentative Cost :
89.44
Exp. Upto Last Fy : 73.28
For CFY 2024-2025
Remaining : 16.16
Demand : 5.00
Allotment : 1.29
Exp in CFY : 4.86
Total Up to Date Exp : 78.15
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 8 months ago
05 Nov 2020
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 04-May-2024
Physical Peramenters