Work Profile

fजला योजना वर्ष 20-21 के अन्तर्गत ज्ञानसू उपला बस्ती मोटर मार्ग से ज्ञानसू-जोंकाणी-पाडुली तक मोटर मार्ग का नव fनमाण कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 104/रा0यो0आ0/जि0यो0/2020-21 दि0 05-11-20

TS Amount (lakhs) : 30 Lacs

Financial Detail

Sanction Cost : 89.44 Lacs

Resanction Cost : 89.44 Lacs

Exp. Upto Last Fy : 73.28 Lacs

For CFY 2024-2025

Remaining : 16.16 Lacs

Demand : 5.00 Lacs

Allotment : 1.29 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 73.28 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 80 %

Up to Date : 80 %

Sanction on :
3 years 6 months ago
05 Nov 2020


Tentative Completion date:
6 months 2 weeks ago
31 Oct 2023


Actual Completion Date:
Not Yet Reported


Rating : 82

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 04-May-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 0.9 0.9 0.000 0.9 0.200 0.000
Currently only Bank Gaurantee information is avilable