Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.65 | 2.65 | 2.650 | 0 | 0.000 | 0.000 |
30W1322 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2319/।।। (2)/21-62 (प्रा0आ0)/2005 टी0सी0 ।।
TS Amount (lakhs) : 62.7 Lacs
Financial Detail
Sanction Cost : 62.70 Lacs
Resanction Cost : 62.70 Lacs
Exp. Upto Last Fy : 41.49 Lacs
For CFY 2024-2025
Remaining : 21.21 Lacs
Demand : 15.00 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 41.49 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
23 Jul 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। अवशेष डिफेक्ट कटिंग का कार्य किया जा रहा है। -- as on 07-May-2024
Physical Peramenters