Work Profile Report [30W1322]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 2319/।।। (2)/21-62 (प्रा0आ0)/2005 टी0सी0 ।।
TS Amount (lakhs) : 62.7 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
62.70
Resanction Cost :
62.70
Tentative Cost :
62.70
Exp. Upto Last Fy :
41.49
For CFY 2024-2025
Remaining :
21.21
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
41.49
Work completed
Sanction on : 3 years 5 months ago
23 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। अवशेष डिफेक्ट कटिंग का कार्य किया जा रहा है। -- as on 07-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand