Work Profile Report [30W1332]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 312/रा0यो0आ0/जि0यो0/2021-22
TS Amount (lakhs) : 3.5 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.50
Resanction Cost :
3.50
Tentative Cost :
3.50
Exp. Upto Last Fy :
2.35
For CFY 2024-2025
Remaining :
1.15
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.35
Work completed
Sanction on : 3 years 4 months ago
26 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 2 years 7 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 04-Oct-2021