Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
30W1339 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 311/रा0यो0आ0/जि0यो0/2021-22
TS Amount (lakhs) : 4 Lacs
Financial Detail
Sanction Cost : 8.00 Lacs
Resanction Cost : 8.00 Lacs
Exp. Upto Last Fy : 4.21 Lacs
For CFY 2024-2025
Remaining : 3.79 Lacs
Demand : 2.00 Lacs
Allotment : 2.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.21 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 99 %
Up to Date : 99 %
Sanction on :
2 years 9 months ago
26 Jul 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 24-Jan-2024